Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : ANUPPUR-KATNI.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1860.9416802311.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1863.5150161929.51

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/202112/20233/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
156.45156.45

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Ongoing

Monthly Status

Background Information

Complete project 165.52 Km commissioned on 31.3.25Singpur Shahdol Badhwabara (13.9 Km) commissioned on 22.03.2024 and Vilayatkala Road Roupond (8.5 Km) section commissioned on 27.03.2024. Total 88.40 Km section out of 165 Km commissioned till March 24. Work is in progress in entire section. NI at Shahdol completed in March.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks