Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : ANUPPUR-KATNI.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   68.69

Time Overrun (Months)-    36

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
137016802311.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1075.43261.4869.761406.67

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/202112/202312/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
266266

Ministry Review Date

LatestLastPhysical Progress (%)Status
74Ongoing

Monthly Status

Background Information

Singpur Shahdol Badhwabara (13.9 Km) commissioned on 22.03.2024 and Vilayatkala Road Roupond (8.5 Km) section commissioned on 27.03.2024. Total 88.40 Km section out of 165 Km commissioned till March 24. Work is in progress in entire section. NI at Shahdol completed in March.44.40 Km out of 165 Km section commissioned till July23, Work is in progress in other sections.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone