Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : KADUR CHIKMAGALUR SAKLESHPUR NEW LINE (93 KM).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
825.31825.31825.31

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
681.975.085.19692.24

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20250/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
135.40

Ministry Review Date

LatestLastPhysical Progress (%)Status
27-NOV-2383Ongoing

Monthly Status

Background Information

"i) Completion Estimate of Kadur -Chikmagalur portion was sanctioned by the Railway Board vide letter dated 21.09.2023. ii) Entire land has been handed over by GoK. iii) Chikamagalur - Hadihalli (9 Km) CRS inspection completed on 29.03.2025. Authorization recieved on 21.04.2025. iv) For the balance section Hadihalli - Belur (12.9 Km) work in progress."i) Completion Estimate of Kadur -Chikmagalur portion after attending the observations of Railway Board was submitted to the Railway Board on 22.06.2023 for a value of Rs.535.21 Cr and the same has been sanctioned by the Railway Board vide letter dated 21.09.2023. ii) Entire land has been handed over by GoK. iii) Chikamagalur - Hadihalli (9 Km) works are in progress. iv) EPC tender for the section between Hadihalli - Belur (13 km) has been opened and is under finalisation.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks