Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : KADUR CHIKMAGALUR SAKLESHPUR NEW LINE (93 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   28

Time Overrun (Months)-    108

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
644.78825.31825.31

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
522.59125.3134.07681.97

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20170/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
7080

Ministry Review Date

LatestLastPhysical Progress (%)Status
27-NOV-2366Ongoing

Monthly Status

Background Information

i) Completion Estimate of Kadur -Chikmagalur portion was sanctioned by the Railway Board vide letter dated 21.09.2023. ii) Entire land has been handed over by GoK. iii) Chikamagalur - Hadihalli (9 Km) works completed and engine rolling done during Feb-2025. CRS inspection completed on 29.03.2025. iv) For the balance section Hadihalli - Belur (12.9 Km), EPC tender was awarded for an amount of Rs. 190.21 Cr on 04.06.2024 and initial planning is under progress.i) Completion Estimate of Kadur -Chikmagalur portion after attending the observations of Railway Board was submitted to the Railway Board on 22.06.2023 for a value of Rs.535.21 Cr and the same has been sanctioned by the Railway Board vide letter dated 21.09.2023. ii) Entire land has been handed over by GoK. iii) Chikamagalur - Hadihalli (9 Km) works are in progress. iv) EPC tender for the section between Hadihalli - Belur (13 km) has been opened and is under finalisation.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone