Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 28
|
Time Overrun (Months)-
99
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
i) Completion Estimate of Kadur -Chikmagalur portion after attending the observations of Railway Board was submitted to the Railway Board on 22.06.2023 for a value of Rs.535.21 Cr and the same has been sanctioned by the Railway Board vide letter dated 21.09.2023.
ii) Entire land has been handed over by GoK.
iii) Chikamagalur - Hadihalli (9 Km) works are in progress.
iv) EPC tender for the section between Hadihalli - Belur (13 km) has been opened and is under finalisation. | 1) The completion estimate with observations was submitted to the Railway board on 12.04.2023 and as directed by Railway Board the MOD duly signed by CE/CN/I/BNC & FA&CAO/CN/BNC and MOD in Hindi format has been submitted to Railway Board on 23.05.2023. Railway board with observations has returned the completion estimate with observations on 14.06.2023 and the same was submitted to Board on 22.06.2023.
2) Chikmagalur - Hadihalli (9 Km) EPC tender has been finalized and LOA has been issued (Rs.121.39 Cr) on 09.02.2023. This section is targeted for commissioning in Mar-2024 and the work is under progress for the same. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |