"i) Completion Estimate of Kadur -Chikmagalur portion was sanctioned by the Railway Board vide letter dated 21.09.2023.
ii) Entire land has been handed over by GoK.
iii) Chikamagalur - Hadihalli (9 Km) CRS inspection completed on 29.03.2025. Authorization recieved on 21.04.2025.
iv) For the balance section Hadihalli - Belur (12.9 Km) work in progress." | i) Completion Estimate of Kadur -Chikmagalur portion after attending the observations of Railway Board was submitted to the Railway Board on 22.06.2023 for a value of Rs.535.21 Cr and the same has been sanctioned by the Railway Board vide letter dated 21.09.2023.
ii) Entire land has been handed over by GoK.
iii) Chikamagalur - Hadihalli (9 Km) works are in progress.
iv) EPC tender for the section between Hadihalli - Belur (13 km) has been opened and is under finalisation. |