Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : BHILDI-VIRAMGAM GAUGE CONVERSION INCLUDING GC OF MAHESANA-TARANGA HILL AS MATERIAL MODIFICATION.

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
551.51724.7890.76

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
757.7215.40773.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/201910/202110/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100

Ministry Review Date

LatestLastPhysical Progress (%)Status
99Completed

Monthly Status

Background Information

Bhildi - Viramgam Section (i) Viramgam-Mehsana GC (64 Km) : Commissioned on 02.12.2004 (ii) Mehsana-Patan GC (40.15 Km) : Commissioned on 14.02.2009 (iii) Patan-Bhildi new line (51.03 Km) : Commissioned on 03.04.2019 (Except Khemana Station Yard. Balance work for commissioning of Khemana statation is in progress. Mahesana - Taranga Hill Section (Section terminated at Varetha Station) Mahesana – Vadnagar Section (34.43 Km) : Commissioned on 23.06.2019 Vadnagar - Varetha Section (20.78 Km) : Commissioned on 11.11.2020 Work of staff quarters & other balance work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks