1.332283.00 Cum Earthwork in cutting has been done during the month.
2.428317.00 Cum Earthwork in filling has been done during the month.
3.Total 2152 Cum PCC & 20351 Cum RCC concrete work was done during the month. total 11039 Cum PCC & 103615 Cum RCC work done in Package 2A,2B,3A,3B and EUP.
4.12- EUP Bridge work started at Bridge No. 77, 95, 109, 121, 137, 139, 145, 180, 181, 200, 213 & 231 in progress.
5.28 no’s Girder has been erected of important Br-03 (30x30.5m) in Urga- Kusmunda section of CEWRC.
| |