Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 12.55
|
Time Overrun (Months)-
87
|
Total/Pending/Completed Milestone -
1
/
1
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Land acquisition of balance Forest land is under acquisition. Fund shortage- Fund availability to be ensured by SPV to expedite the work. | 1.Earthwork and structure work is in progress in Spur line.
2.Blanketing and track linking work is in progress.
3.Br. No. 41A work is in progress.
4.Durgapur feeder line work suspended through mail by CERL.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
Forest Land | 1/2022 | 5/2025 | Pending | Immediate | 7.223 Ha forest land |
Fund constraints | 1/2024 | 4/2025 | Pending | Immediate | Fund to be arranged by SPV |
| Ongoing Milestone | | Completed Milestone | | |