Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : Indian Railway Construction Company Limited.
Project Name : KHARSIA DHARAMJAIGARH WITH SPUR LINE EAST CORRIDOR-PHASE I.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   12.55

Time Overrun (Months)-    69

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
305503438.39

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2774.87233.16.783008.81

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20180/06/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
200200

Ministry Review Date

LatestLastPhysical Progress (%)Status
92.6Ongoing

Monthly Status

Background Information

1.Earthwork and structure work is in progress in Spur line. 2.Blanketing and track linking work is in progress. 3.Br. No. 41A work is in progress. 4.Durgapur feeder line work suspended through mail by CERL. 1.Earthwork and structure work is in progress. 2.Br. No. 41A A1 complete & Pier 1 substructure work had been complete during the month.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Land Acquisition1/20214/2024PendingImmediateSpur Line from 14.50-30.80Km

Ongoing Milestone

Completed Milestone