Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 12.55
|
Time Overrun (Months)-
69
|
Total/Pending/Completed Milestone -
1
/
1
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
1.Earthwork and structure work is in progress in Spur line.
2.Blanketing and track linking work is in progress.
3.Br. No. 41A work is in progress.
4.Durgapur feeder line work suspended through mail by CERL.
| 1.Earthwork and structure work is in progress.
2.Br. No. 41A A1 complete & Pier 1 substructure work had been complete during the month.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
Land Acquisition | 1/2021 | 4/2024 | Pending | Immediate | Spur Line from 14.50-30.80Km |
| Ongoing Milestone | | Completed Milestone | | |