Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : Indian Railway Construction Company Limited.
Project Name : KHARSIA DHARAMJAIGARH WITH SPUR LINE EAST CORRIDOR-PHASE I.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   12.55

Time Overrun (Months)-    87

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
305503438.39

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3008.8167.9635.293112.06

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20180/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
263.6328.4

Ministry Review Date

LatestLastPhysical Progress (%)Status
92.6Ongoing

Monthly Status

Background Information

Land acquisition of balance Forest land is under acquisition. Fund shortage- Fund availability to be ensured by SPV to expedite the work.1.Earthwork and structure work is in progress in Spur line. 2.Blanketing and track linking work is in progress. 3.Br. No. 41A work is in progress. 4.Durgapur feeder line work suspended through mail by CERL.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land1/20225/2025PendingImmediate7.223 Ha forest land
Fund constraints1/20244/2025PendingImmediateFund to be arranged by SPV

Ongoing Milestone

Completed Milestone