Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : Indian Railway Construction Company Limited.
Project Name : KHARSIA DHARAMJAIGARH WITH SPUR LINE EAST CORRIDOR-PHASE I.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
305503438.39

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3112.06.674.513117.24

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20180/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
216.030

Ministry Review Date

LatestLastPhysical Progress (%)Status
92.8Ongoing

Monthly Status

Background Information

1.Earthwork and structure work is in progress in Spur line. 2.Blanketing and track linking work is in progress. 3.Br. No. 41A work is in progress. 4.Durgapur feeder line work suspended through mail by CERL.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Land Acquisition0/00/0OverImmediate
Land Acquisition0/00/0OverImmediate
Forest Land1/20226/2025PendingImmediate7.223 ha forest land acquisition pending