Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH CENTRAL RAILWAY.
Project Name : JHANSI MANIKPUR AND KHAIRAR BHIMSEN DOUBLING.

Reported Date : 09-APR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    36

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4329.5304329.53

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
60.370060.37

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
4000

Ministry Review Date

LatestLastPhysical Progress (%)Status
3Ongoing

Monthly Status

Background Information

•The project envisages the construction of a double line between Jhansi-Khairar-Manikpur & Khairar and Bhimsen & Chord line at Mahoba and Khairar, which would speed up the operation of goods and coaching trains and provide additional capacity for meeting the increase in traffic in future. • At this level of capacity utilization, operations on the section have already reached saturation. In a scenario of demands for introduction of more passenger trains and increasing rail borne freight traffic requiring the running of goods trains, creation of additional line capacity by way of upgradation of signalling, removal of level crossings etc might bring down the line capacity utilization. However, since introduction of additional services on the section without appropriate capacity augmentation measures will only slow down operations and make the section a bottleneck, the double line between Khairar-Bhimsen section is imminent and inescapable.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone