Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH CENTRAL RAILWAY.
Project Name : JHANSI BINA DOUBLING.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 6 / 1 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
200202001

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1713.8611.3220.31745.48

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/04/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
98.790

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-MAY-2590Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks