Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH CENTRAL RAILWAY.
Project Name : JHANSI BINA DOUBLING.

Reported Date : 09-APR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    33

Total/Pending/Completed Milestone - 6 / 4 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
200120012001

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1118.8001118.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/012/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3200

Ministry Review Date

LatestLastPhysical Progress (%)Status
85Ongoing

Monthly Status

Background Information

Lalitpur-Bijrautha is ready for commissioning.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone