Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : MATHURA-JHANSI-3RD LINE (273.80 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   41.13

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3677.7605190.26

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4046.34621.82224.954893.11

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20230/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
365.59365.59

Ministry Review Date

LatestLastPhysical Progress (%)Status
80Ongoing

Monthly Status

Background Information

Total Project length is 259.85 km out of which 187.30 km is commissioned as on March 2024. Remaining 72.54 km is planned to commission before Dec 2024. Planning to commission the project in Dec 2024.The project is under construction phase with cumulative physical progress of 55% and financial progress of 89.40% as on 31.03.2023.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone