Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : NIMACH BADI SADRI NEW LINE PROJECT.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    48

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
495.180495.18

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
112.03127.2226.56265.81

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100149.4

Ministry Review Date

LatestLastPhysical Progress (%)Status
18Ongoing

Monthly Status

Background Information

Tender for Earthwork, Bridgework & Station building in Badi Sadri- Barwara Goojar (21.5Km) is awarded on 04.12.2023 and Work started in available land. Tender for balance Barwara Goojar- Nimach (21.5- 46 Km) is awarded on 02.02.2024 and work is in progress. Land acquisition is in progress. Tender for Earthwork, Bridgework & Station building in Badi Sadri- Barwara Goojar (21.5Km) is awarded on 04.12.2023 and Work started in available land . Tender for balance Barwara Goojar- Nimach (21.5- 46 Km) is awarded on 02.02.2024 and work is in progress in available land.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone