Tenders for all major bridges, minor bridges & Earth work, Transportation girder launching, station building, ballast supply, Track linking have been awarded. Project has been declared as special railway project, section 20A for all the 24 villages has been issued, JM 24 villages completed. Additional Land Acquisition is in progress. Section 20E also issued & 20F notice issued for Anand Prant office. Joint Bank Account for LAQ is opened. ANND-OD(16.95 Km) section Commmisioned.Od-Thasra (21.7 Km), CRS compliance and Final bill work in progress. | Foundation stone laying done by Hon ble Prime Minister Shri Narendra Modi on 04.03.19 at Ahmedabad. Monitoring of this project being done by PMO through PMREF portal under head PM Foundation stone laid projects.Detailed estimate sanctioned by Rly. Board on 25.01.19 vide Rly. Board letter dt 10.06.21, railways requested to plan execution of project on priority & funds for this project will be provided under gross budgetary support (GBS) as originally sanctioned.
The project is targeted by Dec.2024 with assured fund availability. MOR has decided to execute the project throughput EBR (IF).
Targeted section : Anand-Thasra (38.49 Km)
Anand-Od (16.95 Km) : CRS inspected the section on 04.03.24 and certified fit for passenger & goods opening maximum speed of 90 Kmph vide letter dt. 04.03.24.
Od-Thasra (21.7 Km) land available. Works are in progress.
TDC: Phase I: Anand - Od (16.95 Km) -Commissioned
: Od-Thasra (21.7 Km) - Feb.2024/ May.24
: Phase II : Thasra – Timba Road (13.27 Km) - Oct.24
: Timba Road - Godhra (27.04 Km) - Nov.24
|