Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : ANAND GODHRA DOUBLING PROJECT 79 KMS.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    59

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
692.25692.26692.26

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
293.22362.2714.33669.82

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20202/20252/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
50220

Ministry Review Date

LatestLastPhysical Progress (%)Status
97Ongoing

Monthly Status

Background Information

Tenders for all major bridges, minor bridges & Earth work, Transportation girder launching, station building, ballast supply, Track linking have been awarded. Project has been declared as special railway project, section 20A for all the 24 villages has been issued, JM 24 villages completed. Additional Land Acquisition is in progress. Section 20E also issued & 20F notice issued for Anand Prant office. Joint Bank Account for LAQ is opened. ANND-OD(16.95 Km) section Commmisioned.Od-Thasra (21.7 Km), CRS compliance and Final bill work in progress.Foundation stone laying done by Hon ble Prime Minister Shri Narendra Modi on 04.03.19 at Ahmedabad. Monitoring of this project being done by PMO through PMREF portal under head PM Foundation stone laid projects.Detailed estimate sanctioned by Rly. Board on 25.01.19 vide Rly. Board letter dt 10.06.21, railways requested to plan execution of project on priority & funds for this project will be provided under gross budgetary support (GBS) as originally sanctioned. The project is targeted by Dec.2024 with assured fund availability. MOR has decided to execute the project throughput EBR (IF). Targeted section : Anand-Thasra (38.49 Km) Anand-Od (16.95 Km) : CRS inspected the section on 04.03.24 and certified fit for passenger & goods opening maximum speed of 90 Kmph vide letter dt. 04.03.24. Od-Thasra (21.7 Km) land available. Works are in progress. TDC: Phase I: Anand - Od (16.95 Km) -Commissioned : Od-Thasra (21.7 Km) - Feb.2024/ May.24 : Phase II : Thasra – Timba Road (13.27 Km) - Oct.24 : Timba Road - Godhra (27.04 Km) - Nov.24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone