Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : MEHSANA PALANPUR DOUBLING PROJECT 65.10 KMS.

Reported Date : 09-APR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    9

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
537.31537.31537.31

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
130.66286.820417.48

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/202412/202412/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
87.20

Ministry Review Date

LatestLastPhysical Progress (%)Status
72Ongoing

Monthly Status

Background Information

The detailed estimate costing Rs 537.31 Crs. Sanctioned on Dt. 08.09.2020 Vide Rly. Bd letter no. 2019/W-1/WR/SY/DL/PNU-MSH dated 08.09.2020. (A) Land acquisition status: -6.54 Hect land to acquire (B) Bifurcation of total length of project, state wise: -Gujarat – 65.10Km WR (C) Overall progress of project: - Status of Drawings: - • All the 09 Nos. of ESP (PNU, MSH, BHU, UM SID, DRW, Chappi, KMLI & UJA) approved. • No new station buildings are required to be constructed in this project except other miscellaneous buildings. • All the L Section 13 Nos. have been approved by HQ. (Including L section sheet and SID yard alterations) • SIP drawing will be submitted by Railway. All GADs and drawings other than ESPs and SIPs are to be prepared by EPC contr. Planning of commissioning project:- 15 Aug- 2023 MSH - BHANDU Dec.2023 PALANPUR – DHAREWADA Jan – 2024 DHAREWADA - KAMLI Feb - 2024 KAMLI - BHANDU

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone