| The detailed estimate costing Rs 537.31 Crs. Sanctioned on Dt. 08.09.2020 Vide Rly. Bd
letter
no. 2019/W-1/WR/SY/DL/PNU-MSH dated 08.09.2020.
(A) Land acquisition status: -6.54 Hect land to acquire
(B) Bifurcation of total length of project, state wise: -Gujarat – 65.10Km WR
(C) Overall progress of project: -
Status of Drawings: -
• All the 09 Nos. of ESP (PNU, MSH, BHU, UM SID, DRW, Chappi, KMLI & UJA) approved.
• No new station buildings are required to be constructed in this project except other miscellaneous buildings.
• All the L Section 13 Nos. have been approved by HQ. (Including L section sheet and SID yard alterations)
• SIP drawing will be submitted by Railway.
All GADs and drawings other than ESPs and SIPs are to be prepared by EPC contr.
Planning of commissioning project:-
15 Aug- 2023 MSH - BHANDU
Dec.2023 PALANPUR – DHAREWADA
Jan – 2024 DHAREWADA - KAMLI
Feb - 2024 KAMLI - BHANDU
|