Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EASTERN RAILWAY.
Project Name : NARAYANGARH TO BHADRAK 3RD LINE (155 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    37

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1866.3101866.31

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1434.35385.63108.621928.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20230/06/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
548344

Ministry Review Date

LatestLastPhysical Progress (%)Status
58Ongoing

Monthly Status

Background Information

Work in progress. 1) Narayangarh - Belda (12.4 Km) : Commissioned on 03.05.24. 2) Belda-Dantan (16.4 Km) : Commssioned on 22.02.25. 3) Dantan-Jaleswar (16.6 km): Dec-25. 4) Jaleswar-Rupsa (29.5 km): Dec-25. 5) Rupsa-Baleswar (17.9 km): Jun-26. 5) Baleswar-Khantapara (15.4 Km) : Dec-25. 6) Khantapara-Soro (18 km) : Dec-25. 7) Soro-Ranital (21 Km) : Jun-25. 8) Ranital - Ranital (L) (3 Km) 3rd line : Commssioned on 07.03.24. 8) Ranital - Ranital (L) (3 Km) 4th line : Commssioned on 10.01.24. 9) Ranital(L)-Bhadrak (5.74 Km) : ECoR.Work in progress. 1) Narayangarh - Belda (12.4 Km) : Apr-24. 2) Belda-Dantan (16.4 Km) : Nov-24. 3) Dantan-Angua (4.5 km): Jun-25. 4) Angua-Jaleswar (12.1 km): Jun-25. 5) Jaleswar-Balasore (47.4 Km) : Dec-25. 6) Balasore-Soro (33.4 km) : Dec-25. 7) Soro-Ranital (21 Km) : Mar-25. 8) Ranital - Ranital (L) (3 Km) 3rd line : Commssioned on 07.03.24. 8) Ranital - Ranital (L) (3 Km) 4th line : Commssioned on 10.01.24. 9) Ranital(L)-Bhadrak (5.74 Km) : ECoR.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone