Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
37
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
1434.35 | 385.63 | 108.62 | 1928.6 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Work in progress.
1) Narayangarh - Belda (12.4 Km) : Commissioned on 03.05.24.
2) Belda-Dantan (16.4 Km) : Commssioned on 22.02.25.
3) Dantan-Jaleswar (16.6 km): Dec-25.
4) Jaleswar-Rupsa (29.5 km): Dec-25.
5) Rupsa-Baleswar (17.9 km): Jun-26.
5) Baleswar-Khantapara (15.4 Km) : Dec-25.
6) Khantapara-Soro (18 km) : Dec-25.
7) Soro-Ranital (21 Km) : Jun-25.
8) Ranital - Ranital (L) (3 Km) 3rd line : Commssioned on 07.03.24.
8) Ranital - Ranital (L) (3 Km) 4th line : Commssioned on 10.01.24.
9) Ranital(L)-Bhadrak (5.74 Km) : ECoR. | Work in progress.
1) Narayangarh - Belda (12.4 Km) : Apr-24.
2) Belda-Dantan (16.4 Km) : Nov-24.
3) Dantan-Angua (4.5 km): Jun-25.
4) Angua-Jaleswar (12.1 km): Jun-25.
5) Jaleswar-Balasore (47.4 Km) : Dec-25.
6) Balasore-Soro (33.4 km) : Dec-25.
7) Soro-Ranital (21 Km) : Mar-25.
8) Ranital - Ranital (L) (3 Km) 3rd line : Commssioned on 07.03.24.
8) Ranital - Ranital (L) (3 Km) 4th line : Commssioned on 10.01.24.
9) Ranital(L)-Bhadrak (5.74 Km) : ECoR. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |