Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EASTERN RAILWAY.
Project Name : NARAYANGARH TO BHADRAK 3RD LINE (155 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    31

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1866.3101866.31

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
955.38410.2268.751434.35

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20230/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
505447.57

Ministry Review Date

LatestLastPhysical Progress (%)Status
48Ongoing

Monthly Status

Background Information

Work in progress. 1) Narayangarh - Belda (12.4 Km) : Apr-24. 2) Belda-Dantan (16.4 Km) : Nov-24. 3) Dantan-Angua (4.5 km): Jun-25. 4) Angua-Jaleswar (12.1 km): Jun-25. 5) Jaleswar-Balasore (47.4 Km) : Dec-25. 6) Balasore-Soro (33.4 km) : Dec-25. 7) Soro-Ranital (21 Km) : Mar-25. 8) Ranital - Ranital (L) (3 Km) 3rd line : Commssioned on 07.03.24. 8) Ranital - Ranital (L) (3 Km) 4th line : Commssioned on 10.01.24. 9) Ranital(L)-Bhadrak (5.74 Km) : ECoR.Work in progress. 1) Narayangarh - Belda (12.4 Km) : Aug-23/ Oct-23 2) Belda-Jaleswar (33 Km) : Feb-24. 3) Jaleswar-Rajghat (7.5 Km) : 24-25. 4) Rajghat-Rupsa (22 Km) : 24-25. 5) Rupsa-Balasore (17.9 Km) : 24-25. 6) Balasore-Soro:(33.4 km) : Feb-24. 7) Soro-Ranital (21 Km) : Dec-23/ Feb-24. 8) Ranital - Ranital (L) (6 Km) : Aug-23. 9) Ranital(L)-Bhadrak (5.74 Km) : 23-24.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone