Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EASTERN RAILWAY.
Project Name : LODHMA TO PISKA LINK LINE BY PASSING HATIA/RANCHI WITH Y CONNECTION (17.2 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   10.23

Time Overrun (Months)-    48

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
428.650472.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
235.128.442.28265.82

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20220/06/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
6032

Ministry Review Date

LatestLastPhysical Progress (%)Status
2Ongoing

Monthly Status

Background Information

All Land Acquisition Proposal submitted to State Govt. for acquisition. An amount of Rs. 225.90 cr as demanded has been deposited. LA for Pvt. Land in progress. Section 21 completed for all 9 villages. LA for Govt land in 1 village in progress which involve forest diversion, Forest diversion proposal has been uploaded on prawesh portal. Section 37 notice issued to 6 villages. Additional land 2.36 Ha in 3 villages (Pvt. Land: 2.02 Ha, Govt. land: 0.34 Ha ) has been submitted on 14.03.2023 for which sec 11 done on 15.08.23. Payment to Raiyat in Khunti District has been started. Land demarcation work through section intiated. EPC Tender which was supposed to open on 12.12.2023 is cancelled and retender will be done. Fresh EPC Tender to be floated by 30.4.24.All Land Acquisition Proposal submitted to State Govt. for acquisition. An amount of Rs. 225.90 cr as demanded has been deposited. LA for Pvt. Land in progress. Section 21 completed for all 9 villages. LA for Govt land in 1 village in progress which involve forest diversion, Forest diversion proposal has been uploaded on prawesh portal. Section 37 notice issued to 4 villages. Revised Estimate for land requirement is under preparation.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone