Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EASTERN RAILWAY.
Project Name : LODHMA TO PISKA LINK LINE BY PASSING HATIA/RANCHI WITH Y CONNECTION (17.2 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   10.23

Time Overrun (Months)-    48

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
428.650472.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
265.829.65.09275.56

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20220/06/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
4915.31

Ministry Review Date

LatestLastPhysical Progress (%)Status
2Ongoing

Monthly Status

Background Information

All Land Acquisition Proposal submitted to State Govt. for acquisition. An amount of Rs. 225.90 cr as demanded has been deposited. LA for Pvt. Land in progress. Section 21 completed for all 9 villages. LA for Govt land in 1 village in progress which involve forest diversion, Forest diversion proposal has been uploaded on prawesh portal. Section 37 notice issued to 8 villages. Additional land 2.36 Ha in 3 villages (Pvt. Land: 2.02 Ha, Govt. land: 0.34 Ha ) has been submitted on 14.03.2023 for which sec 11 done on 15.08.23. Payment to Raiyat in Khunti District has been started. Land demarcation work 80% completed. Govt. land under DALO Ranchi payment in progress. Dimanteling Structure value under DLAO Ranchi payment in progress. PVT land in Ranchi district 29.95 Ha handed ver by DLAO/Ranchi. PVT land in Khunti district 23.61 Ha handed over by DLAO/Khunti. Longitudinal section revision necessitated due to RNC Divns request, to facilitate future development of new station “Singhpur “ between Lodhma and Piska station. GAD of 2 ROBs approved, GAD of 1 ROB, 3 RUBs & 8 LHS under preparation. Major and Minor Bridge drawings are under preparation. Tender for miscellaneous work like tree cutting, land boundary fixing, dismantling of structure etc. has been finalized and LOA issued on 09.10.2024. Non-EPC tender for execution of main work floated on 23 Jan 2025.All Land Acquisition Proposal submitted to State Govt. for acquisition. An amount of Rs. 225.90 cr as demanded has been deposited. LA for Pvt. Land in progress. Section 21 completed for all 9 villages. LA for Govt land in 1 village in progress which involve forest diversion, Forest diversion proposal has been uploaded on prawesh portal. Section 37 notice issued to 6 villages. Additional land 2.36 Ha in 3 villages (Pvt. Land: 2.02 Ha, Govt. land: 0.34 Ha ) has been submitted on 14.03.2023 for which sec 11 done on 15.08.23. Payment to Raiyat in Khunti District has been started. Land demarcation work through section intiated. EPC Tender which was supposed to open on 12.12.2023 is cancelled and retender will be done. Fresh EPC Tender to be floated by 30.4.24.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone