Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EASTERN RAILWAY.
Project Name : TALGARIA TO BOKARO N/CABIN DOUBLING(38 KM).

Reported Date : 07-NOV-23

Monthly Report : 10 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
390.390513.92

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
380.9857.060438.04

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20210/08/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
520

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks