Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EASTERN RAILWAY.
Project Name : PURULIA TO KOTSHILA DOUBLING (39.1 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   16.52

Time Overrun (Months)-    33

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3380393.83

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
128.62152.0516.59297.26

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20220/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
75142

Ministry Review Date

LatestLastPhysical Progress (%)Status
99Ongoing

Monthly Status

Background Information

Work is in progress. TDC: Kotshila-Gaurinathdham (21.2 km): Commissioned on 29.03.25. Gaurinathdham-Purulia (15 km): Commissioned on 29.03.25.Work is in progress. TDC: Kotshila-Gaurinathdham (21.2 km): Dec-24 Gaurinathdham-Purulia (15 km): Dec-24.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone