Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : JEYPORE MALKANGIRI NEW LINE.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
642.690642.69

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
131.5368.80200.33

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20330/07/2033

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
.1Ongoing

Monthly Status

Background Information

Total 1118 Acr of forest land diversion Stage-I clearance obtained this month.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone