Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : GANDHAMARDAN IRON ORE MINES TO GOALDIH STATION.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    6

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
189.930189.93

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
05.198.5713.76

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20270/03/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2020

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

1. The work was sanctioned in 2019-20 vide PB item no-30 at a cost of Rs.151.50 Cr. 2. Final Location Survey completed & Detailed Estimate at a cost of Rs.257.98 Cr sanctioned on 30.12.2022. 3. Land Acquisition in process as per Spl. Rly. Act & 20E e-Gaz. notice published on 29.11.24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone