Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : GANDHAMARDAN IRON ORE MINES TO GOALDIH STATION.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
189.930189.93

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
13.76.28014.04

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20270/03/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
28.60

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

DPR Sanctioned on 09.09.2022 Land Acquisition through Railway Act is in Progress e-Gaz. Notification 20E was published on 02.04.2024. ESTIMATE IS UNDER SANCTION.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks