Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : BAGHUAPAL FLY OVER (20 KM).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
183257.97257.97

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
.6.230.83

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20278/20278/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
67.050

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

The project was sanctioned in 2019-20. The detailed estimate sanctioned for Rs 257.97 Cr on 30.12.2022.Land acquisition in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks