Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : DARBHANGA - BYPASS LINE CONNECTING SHISHO HALT AND KAKARGHATI EXCL DARBHANGA YARD (7.64 KM).

Reported Date : 15-MAY-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
983.62253.23415

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
417.5700417.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20250/010/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Darbhanga Bye pass (9.48 Km) - E/W & Blanketing - Work in progress, Minor Br. - Total 10 no Br. completed out of 14 no br., Major Br. - Work in progress (Substructure of Br. No. 30 completed.), Station building - Completed, OHE work-in progress.Target month of commissioning - April 24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks