Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : BARAUNI- BACHWARA 3RD AND 4TH LINE.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    -19

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4860486

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
47.0870.076.76123.91

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20270/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
70104.75

Ministry Review Date

LatestLastPhysical Progress (%)Status
33Ongoing

Monthly Status

Background Information

Barauni - Bachhwara :- E/Work - Work in Progress, Minor Bridges - 11 nos bridge completed out of 22 nos bridge, Station Buildings - Work in progress, OHE work - Work in progress. Target month of commissioning - Dec 25"FLS completed, Project has been sanctioned by Rly. Boards letter no. 2022/W-2/ECR/DL/DPR/07 (3386782), dated- 07.10.2022. Tender for Formation, Bridges, Building & Yard work awarded. Work in progress.Target month of commissioning - June-25"