Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : BARAUNI- BACHWARA 3RD AND 4TH LINE.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4860486

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
123.9104.52128.43

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20270/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
500

Ministry Review Date

LatestLastPhysical Progress (%)Status
33Ongoing

Monthly Status

Background Information

Barauni - Bachhwara :- E/Work - Work in Progress, Minor Bridges - Work in Progress, Station Buildings - Work in progress, OHE work - Work in progress. Target month of commissioning - Mar 26"FLS completed, Project has been sanctioned by Rly. Boards letter no. 2022/W-2/ECR/DL/DPR/07 (3386782), dated- 07.10.2022. Tender for Formation, Bridges, Building & Yard work awarded. Work in progress.Target month of commissioning - June-25"

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks