Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : SURFACE TRIANGLE LINE BETWEEN BHADURA STATION AND NEW CROSSING STN KARMA DOUBLING.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
199.960199.96

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
055055

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20270/010/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

DPR-cum-Detailed Estimate has been vetted by RB vide letter No. 2022/W-II/ECR/DL/10 (3407075) dated 6.10.22. EPC in under process. Land acquisition under rail each under process.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone