Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : SURFACE TRIANGLE LINE BETWEEN BHADURA STATION AND NEW CROSSING STN KARMA DOUBLING.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
199.960199.96

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
55.090055.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20270/010/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
7070

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

Status of Land Acquisition :- Total 29.167 ha land required for new surface line and new Karma Yard at proposed station Karma. 20E uploaded on e Gazette on 22.11.2023. Rs 55 crore has been deposited to State Govt. on 30.12.2023. Rs 15 lakh also demanded by state govt for Establishment cost which has been paid. Disbursement of payment is in progress (completed for 7.33 Ha) Bhadaura - Karma (11.1 km) - Work in progress. Target month of commissioning Feb 27DPR-cum-Detailed Estimate has been vetted by RB vide letter No. 2022/W-II/ECR/DL/10 (3407075) dated 6.10.22. EPC in under process. Land acquisition under rail each under process.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks