Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Status of Land :- Under Acquisition. Total land required is 29.167 Ha. 20E published on 22.11.2023. Rs 55 crore has been deposited to State Govt. Letter from ADM for acceptance of rate decided by state Govt. 31.12.2024. Letter given for go ahead on 08.01.2025, 11.01.2025 & 20.01.2025. Letter sent by ADM to tehsildar for document submission by land losers.
Bhadaura - Karma (11.0 km) - Work in progress. Target month of commissioning Dec 26 | DPR-cum-Detailed Estimate has been vetted by RB vide letter No. 2022/W-II/ECR/DL/10 (3407075) dated 6.10.22. EPC in under process. Land acquisition under rail each under process.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |