Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : SURFACE TRIANGLE LINE BETWEEN BHADURA STATION AND NEW CROSSING STN KARMA DOUBLING.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
199.960199.96

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
55.090055.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20270/010/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
7070

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

Bhadaura - Karma (11.1 km) - Work in progress. Target month of commissioning Feb 27 Status of Land Acquisition :- Land acquisition of 29.167 Ha is involved. Rs 55 Cr. deposited to State Govt. on 30.12.2023. Disbursement of payment is in progress. Notification under 37A issued on 19.12.2022. Notification under 7A issued on 31.01.2023. Land Acquisition Plan has been submitted on 01.02.2023 & 03.08.2023. Notification under 20A issued on 05.07.2023. Notification under 20E issued on 22.11.2023. Land cost demanded by State Govt. on 13.10.2023 Payment done Rs. 30.42 Cr. for 8.29 Ha land.DPR-cum-Detailed Estimate has been vetted by RB vide letter No. 2022/W-II/ECR/DL/10 (3407075) dated 6.10.22. EPC in under process. Land acquisition under rail each under process.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks