Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
-15
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
"Detailed Estimate has been sanctioned with total cost of Rs. 496.367 Cr.vide Railway Board Letter No. 2019/W-2/ECR/NL/02, New Delhi dated 15.02.2019 and revised detail estimate was sanctioned after FLS, at total cost of Rs. 588.18 Cr. in Mar 23. Workis in progress, L-section approved. GAD under preparation. ROR report is received from DNR Division. Project declared as special Railway Project. Notification for special Railway Project & CALA has been done. Land acquisition filed and land verification in process.
Target month of commissioning Mar-2027
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |