Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : JHAJHA - BATIA (UMBRELLA WORK PB#23/2018-19/NR).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    -15

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
496.470496.47

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1.11.2201.33

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20280/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

"Detailed Estimate has been sanctioned with total cost of Rs. 496.367 Cr.vide Railway Board Letter No. 2019/W-2/ECR/NL/02, New Delhi dated 15.02.2019 and revised detail estimate was sanctioned after FLS, at total cost of Rs. 588.18 Cr. in Mar 23. Workis in progress, L-section approved. GAD under preparation. ROR report is received from DNR Division. Project declared as special Railway Project. Notification for special Railway Project & CALA has been done. Land acquisition filed and land verification in process. Target month of commissioning Mar-2027

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone