Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : SONENAGAR BYE PASS LINE FROM CHIRALAPOTHU TO BAGHA BISHUNPUR.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
234223.69223.69

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
22.570022.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20270/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
15.240

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

Project sanctioned vide Railway Board Letter No. 2021/W-II/ECR/DL/07 (3348394) New Delhi, dated 07.10.2022 for total cost of Rs 223.69 Cr. DPR cum DE vetted for the cost of Rs 223.69 Cr. sanctioned by Railway Board on 07.10.2022. Project is declared a Special Railway Project by GM/ECR. Total land acquisition involved is 29.36-acre. 20E published. 19.85-acre land received. EPC tender for all works incl. Engg., S&T and Electrical invitation. Target month of commissioning March 27. Sanctioned by Railway Board for the cost of Rs. 223.69 Cr.on 07.10.2022. Project is sanctioned under special Railway Project by GM/ECR. Total land acquisition involved 28.3097 acre. 20E published . Land acquisition work under progress. Physical progress of work is 0. Expenditure occurred in preparation of Drawing etc.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks