Project sanctioned vide Railway Board Letter No. 2021/W-II/ECR/DL/DPR/06 (3347170) New Delhi, dated 21.11.2022.
i) Pradhankhunta – Rakhitpur (7.28 km):- E/work - 2.69 Lcum out of 2.92 Lcum completed. & Blanketing - 11808 cum out of 26474 cum completed, Minor Br./LHS/RUB - 2+6 no box Completed out of total 12 no br. & Station Building - Work in progress & OHE work in progress.Targeted month of commissioning in Mar’26.
ii) Rakhitpur - Sindri BH (7.19 km) :- E/Work- complete, Blanketing - 4487 cum out of 22100 cum completed, Minor Br./LHS/RUB - 7 no br. Completed out of total 11 no br. & Station Building - Work in progress & OHE work in progress. Targeted month of commissioning in Mar’26.
iii) Sindri BH - Patherdih (3.12 km) - ):- E/Work- 7.093 Lcum out of 11.15 Lcum completed., Minor Br./LHS/RUB - Work in progress & Station Building - Work in progress. & OHE work in progress. Targeted month of commissioning on Mar’26. | Project sanctioned vide Railway Board Letter No. 2021/W-II/ECR/DL/DPR/06 (3347170) New Delhi, dated 21.11.2022. EPC tender for Pradhankhunta-sindri BH finalised on 01/12/2023 and for Sindri BH- Patherdih opened on 26.03.24.
Targeted month of commissioning in Mar 26. |