Project sanctioned vide Railway Board Letter No. 2021/W-II/ECR/DL/DPR/06 (3347170) New Delhi, dated 21.11.2022. Land acquisition in progress.
i) Pradhankhunta – Rakhitpur (7.28 km):- E/Work - 2.7 out of 2.92 Lcum completed, Blanketing - work in progress, Minor bridge -2 nos. Completed out of total 12 no br. & Station Building - Work in progress. Targeted month of commissioning in Mar’26.
ii) Rakhitpur - Sindri BH (7.19 km) :- E/Work- completed, Station Building - Work in progress. Minor Br/ LHS/RUB - 6 nos Br. completed out of total 11 nos Br., Targeted month of commissioning in Mar’26.
iii) Sindri BH - Patherdih (3.12 km) - ):- E/Work- (90%) complete, Work in progress & Station Building - Work in progress. Targeted month of commissioning on Mar’26. | Project sanctioned vide Railway Board Letter No. 2021/W-II/ECR/DL/DPR/06 (3347170) New Delhi, dated 21.11.2022. EPC tender for Pradhankhunta-sindri BH finalised on 01/12/2023 and for Sindri BH- Patherdih opened on 26.03.24.
Targeted month of commissioning in Mar 26. |