Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : DOUBLING OF PRADHANKHUNTA JN -PATHERDIH BAZAR-BHOJUDIH.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
202349.22349.22

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
55.432.336.3464.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20270/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
800

Ministry Review Date

LatestLastPhysical Progress (%)Status
2Ongoing

Monthly Status

Background Information

Project sanctioned vide Railway Board Letter No. 2021/W-II/ECR/DL/DPR/06 (3347170) New Delhi, dated 21.11.2022. Land acquisition in progress. i) Pradhankhunta – Rakhitpur (7.28 km):- E/Work - 2.7 out of 2.92 Lcum completed, Blanketing - work in progress, Minor bridge -2 nos. Completed out of total 12 no br. & Station Building - Work in progress. Targeted month of commissioning in Mar’26. ii) Rakhitpur - Sindri BH (7.19 km) :- E/Work- completed, Station Building - Work in progress. Minor Br/ LHS/RUB - 6 nos Br. completed out of total 11 nos Br., Targeted month of commissioning in Mar’26. iii) Sindri BH - Patherdih (3.12 km) - ):- E/Work- (90%) complete, Work in progress & Station Building - Work in progress. Targeted month of commissioning on Mar’26.Project sanctioned vide Railway Board Letter No. 2021/W-II/ECR/DL/DPR/06 (3347170) New Delhi, dated 21.11.2022. EPC tender for Pradhankhunta-sindri BH finalised on 01/12/2023 and for Sindri BH- Patherdih opened on 26.03.24. Targeted month of commissioning in Mar 26.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

   <