Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : Rampurhat-Murarai (29.48 km)-3rd line.

Reported Date : 25-APR-24

Monthly Report : 4 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
218.030218.03

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
36.19030.9567.14

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/012/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
63.640

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

COMPLETED & COMMISSIONED ON 21.12.2023. Dedicated to the nation by Hon’ble Prime Minister on 2nd March, 2024 at Krishnanagar(WB.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks