Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : CHITRA - BASUKINATH (38.30 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
827.890793.87

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
179.7802.85182.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20263/20273/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100113.95

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

1) The project has been sanctioned based on consent letter from Govt. of Jharkhand for 50:50 cost sharing. Land acquisition is in progress. 2) Till date Rs. 285.30 Cr. payment made to State Government. Possession of 48.225 acre of Private land in 8 Mouza out of 15 in Dumka district and possession of 236.140 Acre of private land in 30 Mouza out of 43 in Deoghar district has been done. 3) MOU for cost sharing has been submitted to Government of Jharkhand on 20.04.24 for approval. Further reminder has been given to Railway Board letter 08.11.23. But till date, approval of MOU for cost sharing is awaited. It has been informed to the Secretary Transport/ Government of Jharkhand that no decision has been taken by Higher Authority.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone