Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
12
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
1) The project has been sanctioned based on consent letter from Govt. of Jharkhand for 50:50 cost sharing. Land acquisition is in progress.
2) Till date Rs. 285.30 Cr. payment made to State Government. Possession of 48.225 acre of Private land in 8 Mouza out of 15 in Dumka district and possession of 236.140 Acre of private land in 30 Mouza out of 43 in Deoghar district has been done.
3) MOU for cost sharing has been submitted to Government of Jharkhand on 20.04.24 for approval. Further reminder has been given to Railway Board letter 08.11.23. But till date, approval of MOU for cost sharing is awaited. It has been informed to the Secretary Transport/ Government of Jharkhand that no decision has been taken by Higher Authority. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |