Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : 4TH LINE BETWEEN BAREJADI NANDEJ (GERATPUR)- SANAND (38.20 KM) (AHMEDABAD BYPASS)..

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    -1

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
961.67961.67961.67

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
97.341.224.58103.14

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20272/20272/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10200

Ministry Review Date

LatestLastPhysical Progress (%)Status
16Ongoing

Monthly Status

Background Information

Contract for Important Bridge (Sabarmati) awarded in Feb’24. Work is in progress. Tender for other works including Minor Bridge, Earthwork etc. is under process of invitation. For the 4th Line between Barejadi Nandej (Geratpur)-Sanand and New BG Line Intersection (05 Nos.) Between Geratpur- Sanand & Botad- Ahmedabad project, two tenders were opened jointly, and the third tender is under approval.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Land Acquisition0/00/0PendingImmediate