Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
-1
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Contract for Important Bridge (Sabarmati) awarded in Feb’24. Work is in progress.
Tender for other works including Minor Bridge, Earthwork etc. is under process of invitation.
For the 4th Line between Barejadi Nandej (Geratpur)-Sanand and New BG Line Intersection (05 Nos.) Between Geratpur- Sanand & Botad- Ahmedabad project, two tenders were opened jointly, and the third tender is under approval.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
Land Acquisition | 0/0 | 0/0 | Pending | Immediate | |
| Ongoing Milestone | | Completed Milestone | | |