Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : MEHSANA-PALANPUR (65.1 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   1.51

Time Overrun (Months)-    -21

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
529.30537.31

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
047.67047.67

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20260/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
87.2185.5

Ministry Review Date

LatestLastPhysical Progress (%)Status
75Ongoing

Monthly Status

Background Information

Laying of foundation stone of project done by Honble PM shri Narendra Modi on 18.06.22.Detailed estimate sanctioned on 8.9.20. Land : Main project is not affected by Land Acquisition. 5.93 Ha Private land for service roads to be acquired. Between Section Mahesana – Unjha - Notification Under Section 20A(1) completed. JMS is pending. Money deposited with district administration for JMS. JMS to be conducted by State authority. Status of Tenders:- All contracts has been awarded. esana- Bhandu Motidau (8.87Km) : Commissioned (ii) Palanpur- Dharewada (24.085Km) :Commissioned (iii) Dharewada- Kamli (11.87km) : Mar. 24/ Apr.24 (iv) Kamli-Bhandu Motidau (21.15 km) : Mar 24/ June 24