Planning of commissioning of various sections is as below:
Rajkot - Paddhari (24.80 Km)- Commissioned on 29.06.2024
Paddhari - Hadmatiya (14.00 Km)- Commissioned on 03.03.2025.
Lakhabawal-Kanalus (14.83 Km)- June-2025
Jamnagar-Lakhabawal (11.60 km) - Dec-2025
Aliyavada- Hapa-Jamnagar (18.58 Km)- Feb-2026
Jamwanthali- Aliyavada (11.76 Km)- May-2026
Hadmatiya-Jamwanthali (15.63 Km)- June-2026
Contract for all works is awarded.
Work is in progress in all the balance sections.
| Laying of foundation stone of project done by Honble PM shri Narendra Modi on 18.06.22.
Detailed estimate sanctioned on 8.9.20. Land : Main project is not affected by Land Acquisition. 5.93 Ha Private land for service roads to be acquired. Between Section Mahesana – Unjha - Notification Under Section 20A(1) completed. JMS is pending. Money deposited with district administration for JMS.
JMS to be conducted by State authority.
Status of Tenders:- All contracts has been awarded.
Progress : (i) Mahesana- Bhandu Moti Dau (8.87 Km) : CRS inspected the section on 25.08.23 and certified fit for passenger & goods opening with maximum speed of 90 Kmph with diesel traction vide letter dt. 25.08.23.Work is in progress.
TDC :
(i) Mahesana- Bhandu Motidau (8.87Km) : Commissioned
(ii) Palanpur- Dharewada (24.085Km) :Commissioned
(iii) Dharewada- Kamli (11.87km) : Mar. 24/ Apr.24
(iv) Kamli-Bhandu Motidau (21.15 km) : Mar 24/ June 24 |