Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 6.81
|
Time Overrun (Months)-
-19
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Laying of foundation stone of project done by Honble PM shri Narendra Modi on 18.06.22.
Detailed estimate sanctioned on 8.9.20. Land : Main project is not affected by Land Acquisition. 5.93 Ha Private land for service roads to be acquired. Between Section Mahesana – Unjha - Notification Under Section 20A(1) completed. JMS is pending. Money deposited with district administration for JMS.
JMS to be conducted by State authority.
Status of Tenders:- All contracts has been awarded.
Progress : (i) Mahesana- Bhandu Moti Dau (8.87 Km) : CRS inspected the section on 25.08.23 and certified fit for passenger & goods opening with maximum speed of 90 Kmph with diesel traction vide letter dt. 25.08.23.Work is in progress.
TDC :
(i) Mahesana- Bhandu Motidau (8.87Km) : Commissioned
(ii) Palanpur- Dharewada (24.085Km) :Commissioned
(iii) Dharewada- Kamli (11.87km) : Mar. 24/ Apr.24
(iv) Kamli-Bhandu Motidau (21.15 km) : Mar 24/ June 24
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |