Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : NIMACH-RATLAM (133 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   20.43

Time Overrun (Months)-    -31

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
9101095.881095.88

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0434.220434.22

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20273/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
4000

Ministry Review Date

LatestLastPhysical Progress (%)Status
35Ongoing

Monthly Status

Background Information

Detailed project report/detailed estimate of Ratlam Nimach Doubling Project (132.92 Km) sanctioned by Railway Board on 07.10.2021. TDC -March-2025 • Consultancy tender awarded • EPC and Composite Tenders have been awarded for Nimach-Dalauda (63.49 Kms) section and Dalauda-Ratlam (69.43 Kms) section. Tender for Project Supervision Services awarded. Tender for Electronic Interlocking awarded. Status of land acquisition, drawings and works are being attached. Namli-Dhoswas 11.796 Km section commissioned on 20.03.24. Work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone