Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : NIMACH-RATLAM (133 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   20.43

Time Overrun (Months)-    -28

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
9101095.881095.88

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
434.22512.7354.341001.29

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20276/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400530

Ministry Review Date

LatestLastPhysical Progress (%)Status
72Ongoing

Monthly Status

Background Information

Detailed Project Report/Detailed estimate of RTM-NMH Doubling Project 132.92 Km sanctioned by Rly Brd on 07.10.21 • Consultancy tender awarded • EPC & Composite Tenders awarded for Nimach-Dalauda 63.49 Kms sect & Dalauda-Ratlam 69.43 Kms sect. Tender for PSS awarded. Tender for EI awarded. Status of land acquisition, drawings and works arDetailed project report/detailed estimate of Ratlam Nimach Doubling Project (132.92 Km) sanctioned by Railway Board on 07.10.2021. TDC -March-2025 • Consultancy tender awarded • EPC and Composite Tenders have been awarded for Nimach-Dalauda (63.49 Kms) section and Dalauda-Ratlam (69.43 Kms) section. Tender for Project Supervision Services awarded. Tender for Electronic Interlocking awarded. Status of land acquisition, drawings and works are being attached. Namli-Dhoswas 11.796 Km section commissioned on 20.03.24. Work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   <