Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : HIMMATNAGAR-KHEDBRAHMA (54.83 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   35.9

Time Overrun (Months)-    -59

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
354.99482.43482.43

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
078.66078.66

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20300/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1000

Ministry Review Date

LatestLastPhysical Progress (%)Status
12Ongoing

Monthly Status

Background Information

Estimate sanctioned by Railway Board vide letter dt.02.06.2022. Lay foundation stone of project done by Honble PM shri Narendra Modi on 18.06.22. Land aquisition not required. EPC tender awarded on 28.05.23. Work is in progress. TDC : 31 Km - Dec.24 (Himmatnagar-Idar) : 23.83 Km - Mar.25 (Idar -Khedbrahma)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone