Work is in progress in whole stretch of the project.
1. Himmatnagar –Idar (31 Km) - Engine trial done on 30.03.2025 in between Himmatnagar-Idar section
(31.00KM) Physical progress - 98%
2. Idar – Khedbrahma (23.83 Km) - Engine trial done on 30.03.2025 in between Idar-Vadali section (11.00KM) Physical progress - 84%
Commissioning for whole project planned in June-2025
| Estimate sanctioned by Railway Board vide letter dt.02.06.2022. Lay foundation stone of project done by Honble PM shri Narendra Modi on 18.06.22. Land aquisition not required.
EPC tender awarded on 28.05.23. Work is in progress.
TDC : 31 Km - Dec.24 (Himmatnagar-Idar)
: 23.83 Km - Mar.25 (Idar -Khedbrahma) |