Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : HIMMATNAGAR-KHEDBRAHMA (54.83 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   35.9

Time Overrun (Months)-    -56

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
354.99482.42482.42

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
78.66691.5743.14813.37

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20306/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
90150

Ministry Review Date

LatestLastPhysical Progress (%)Status
84Ongoing

Monthly Status

Background Information

Work is in progress in whole stretch of the project. Two sections have been identified 1. Himmatnagar –Idar (31 Km) - Engine trial done on 30.03.2025 in between Himmatnagar-Idar section (31.00KM) Physical progress - 98% 2. Idar – Khedbrahma (23.83 Km) - Engine trial done on 30.03.2025 in between Idar-Vadali section (11.00KM) Physical progress - 65% Commissioning for whole project planned in June-2025Estimate sanctioned by Railway Board vide letter dt.02.06.2022. Lay foundation stone of project done by Honble PM shri Narendra Modi on 18.06.22. Land aquisition not required. EPC tender awarded on 28.05.23. Work is in progress. TDC : 31 Km - Dec.24 (Himmatnagar-Idar) : 23.83 Km - Mar.25 (Idar -Khedbrahma)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone