Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : HIMMATNAGAR-KHEDBRAHMA (54.83 KM).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
354.99482.42482.42

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
287.3421.161.25309.75

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20306/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
90150

Ministry Review Date

LatestLastPhysical Progress (%)Status
91Ongoing

Monthly Status

Background Information

Work is in progress in whole stretch of the project. 1. Himmatnagar –Idar (31 Km) - Engine trial done on 30.03.2025 in between Himmatnagar-Idar section (31.00KM) Physical progress - 98% 2. Idar – Khedbrahma (23.83 Km) - Engine trial done on 30.03.2025 in between Idar-Vadali section (11.00KM) Physical progress - 84% Commissioning for whole project planned in June-2025 Estimate sanctioned by Railway Board vide letter dt.02.06.2022. Lay foundation stone of project done by Honble PM shri Narendra Modi on 18.06.22. Land aquisition not required. EPC tender awarded on 28.05.23. Work is in progress. TDC : 31 Km - Dec.24 (Himmatnagar-Idar) : 23.83 Km - Mar.25 (Idar -Khedbrahma)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks