Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 35.9
|
Time Overrun (Months)-
-56
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Work is in progress in whole stretch of the project. Two sections have been identified
1. Himmatnagar –Idar (31 Km) - Engine trial done on 30.03.2025 in between Himmatnagar-Idar section (31.00KM) Physical progress - 98%
2. Idar – Khedbrahma (23.83 Km) - Engine trial done on 30.03.2025 in between Idar-Vadali section (11.00KM) Physical progress - 65%
Commissioning for whole project planned in June-2025 | Estimate sanctioned by Railway Board vide letter dt.02.06.2022. Lay foundation stone of project done by Honble PM shri Narendra Modi on 18.06.22. Land aquisition not required.
EPC tender awarded on 28.05.23. Work is in progress.
TDC : 31 Km - Dec.24 (Himmatnagar-Idar)
: 23.83 Km - Mar.25 (Idar -Khedbrahma) |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |