Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : PETLAD-BHADRAN (22.5 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   51.66

Time Overrun (Months)-    -53

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
202.5307.12307.12

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
02.0902.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20300/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
300

Ministry Review Date

LatestLastPhysical Progress (%)Status
1Ongoing

Monthly Status

Background Information

Detailed Estimate sanctioned by Railway Board vide letter dt. 17.05.2022. Lay foundation stone of project done by Honble PM shri Narendra Modi on 18.06.22. Approximately 51.84 Ha (2.0772 Ha Govt. + 49.7653 Ha. Pvt) land in 21 villages (8 Govt.+13 Pvt.) required. The project declared as Special Railway Project. Special land acquisition officer was nominated. 20E published for 13 villages (29.0139 ha) out of 13 villages on dated 7.11.2023 & 19.12.2023. Additional 20A issued for all villages (15.1035)on 29.02.2024 and additional 20E will be published on 31.03.2024. EPC contract for completee section awarded on 19.10.23. Work commenced.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone