Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : NADIAD-PETLAD (37.26 KM).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
335.34461.91461.91

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
73.23.06.8274.11

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20300/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
820

Ministry Review Date

LatestLastPhysical Progress (%)Status
7Ongoing

Monthly Status

Background Information

Detailed project report/detailed estimate of Nadiad - Petlad GC project was sanctioned by Rly. Board vide letter No.2022/W-I/WR/GC/DPR/ND-PTD dt.17.05.2022. L Sections & ESPs are under approval. Land acquisition is completed. Tender is awarded on 19.10.23. Joint Bank Account for LAQ is opened. Earthwork and excavation for bridges started.Detailed Estimate sanctioned by Railway Board vide letter dt. 17.05.2022. Lay foundation stone of project done by Honble PM shri Narendra Modi on 18.06.22. The project declared as Special Railway Project under clause 37A of Railway (Amendment) Act 2008 by competent authority on 08.07.2022. Special Land Acquisition Officer has been nominated. Total land required(56.3445 Ha) for 13 Village, 20E published for 11 villages (19.1724 ha) out of 13 villages on dated : 20.12.2023 & 16.02.2024 Proposal for the additional survey numbers in the alignment submitted to SDM/Nadiad for 06 villages (13.494 ha) on dated : 27.02.2024 . SDM/PETLAD issue 20E for additional survey number in alignment for six villages (23.6781 ha ) on dated 06.03.2024. 01 Village (Virol) is in process due to consolidation. EPC tender EPC Tender awarded on 20.10.2023 for Earth work, Major & Minor Bridges and Station Building & Other Structures. Works are in progress. TDC (i) Nadiad- Dewa ( 19.00 Km):-Dec.25 (ii) Dewa-Petlad(18.26 Km):- Dec-25

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks