Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 37.74
|
Time Overrun (Months)-
-54
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Detailed Estimate sanctioned by Railway Board vide letter dt. 17.05.2022. Lay foundation stone of project done by Honble PM shri Narendra Modi on 18.06.22.
The project declared as Special Railway Project under clause 37A of Railway (Amendment) Act 2008 by competent authority on 08.07.2022. Special Land Acquisition Officer has been nominated.
Total land required(56.3445 Ha) for 13 Village, 20E published for 11 villages (19.1724 ha) out of 13 villages on dated : 20.12.2023 & 16.02.2024 Proposal for the additional survey numbers in the alignment submitted to SDM/Nadiad for 06 villages (13.494 ha) on dated : 27.02.2024 . SDM/PETLAD issue 20E for additional survey number in alignment for six villages (23.6781 ha ) on dated 06.03.2024. 01 Village (Virol) is in process due to consolidation.
EPC tender
EPC Tender awarded on 20.10.2023 for Earth work, Major & Minor Bridges and Station Building & Other Structures. Works are in progress.
TDC (i) Nadiad- Dewa ( 19.00 Km):-Dec.25
(ii) Dewa-Petlad(18.26 Km):- Dec-25 | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |