Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : SAMLAYA-TIMBA ROAD (53.53 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   66.92

Time Overrun (Months)-    -44

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
401.48670.17670.17

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
14.5361.095.881.42

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20307/20267/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
9010.48

Ministry Review Date

LatestLastPhysical Progress (%)Status
12Ongoing

Monthly Status

Background Information

Tender for Major bridge (09 Nos) works awarded to M/s Manglam on 10.05.2024 with DOC of 18months. mobilization of equipments, establishment of site laboratory completed. soil investigation of major bridges completed. Working piles 18/18 for br 67, 18/18 for br 69, 44/48 for Br. 106, Raft Foundation for Br. no. 83, 115 completed. Fabrication of girders for 04 spans of 18.3 m Composite girder completed and offered for inspection to FIU.Detailed Estimate sanctioned by Railway Board vide letter dt. 3.02.2023. SRP notification on 08.02.23 and competent authority notification on 28.03.23. Land Acquisition proposal for issuing 20A notification submitted on 10.04.23. 20A notification issued on 20.11.23. JMS in progress, 4/25 completed. EPC tender to be invited after land acquisition. EPC tender for rest of work is in preparation. Critical Issues: Land acquisition. 93 hectare land required [only 61% of required land available] Wonder Cement Siding,Tulsigram - Timba-Tulsigram section planned only for Goods during the year. Timba to WCL-GCT section GC work inspected by committee on 8.03.2024 and certified fit for goods traffic @ 30 Kmph from Timba to WCL vide letter dt. 12.03.2024. TDC : 4.5 Km: Commissioned for Goods (Timba-WCL) 10.0 Km: Dec.25 (Timba-Desar Road) 39.0 Km: July.26 (Desar Road-Samlaya)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone