Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 66.92
|
Time Overrun (Months)-
-53
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Detailed Estimate sanctioned by Railway Board vide letter dt. 3.02.2023. SRP notification on 08.02.23 and competent authority notification on 28.03.23. Land Acquisition proposal for issuing 20A notification submitted on 10.04.23. 20A notification issued on 20.11.23. JMS in progress, 4/25 completed.
EPC tender to be invited after land acquisition. EPC tender for rest of work is in preparation.
Critical Issues: Land acquisition. 93 hectare land required [only 61% of required land available]
Wonder Cement Siding,Tulsigram - Timba-Tulsigram section planned only for Goods during the year. Timba to WCL-GCT section GC work inspected by committee on 8.03.2024 and certified fit for goods traffic @ 30 Kmph from Timba to WCL vide letter dt. 12.03.2024.
TDC : 4.5 Km: Commissioned for Goods (Timba-WCL)
10.0 Km: Dec.25 (Timba-Desar Road)
39.0 Km: July.26 (Desar Road-Samlaya) | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |