Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : SAMLAYA-TIMBA ROAD (53.53 KM).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
670670.17670.17

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
81.427.8912.48101.79

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20307/20267/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
73.80

Ministry Review Date

LatestLastPhysical Progress (%)Status
12Ongoing

Monthly Status

Background Information

Tender for Major bridge 09 Nos works awarded to Ms Manglam on 10.05.2024 with DOC of 18months. mobilization of equipments, establishment of site laboratory completed. soil investigation of major bridges completed. 1.Br no 67 - A1&A2-9N9 piles completed. Pile cap completed. 2.Br no 69- A1&A2 all piles completed. Abutment cap completed. A1-Return wall 3rd lift completed. A2-Return wall 4th lift completed. 3.Br no 83- A1&A2 Abutment cap completed. Return wall 7th lift completed. 4.Br no 87-A1 -9N9 piles completed. P1 - Raft complete. pier completed. P2- Raft completed. P3- nil. P4- Raft foundation completed. 1st lift completed. P5- Raft completed. A2- Raft foundation completed. 5th lift of abutment completed. 2nd lift of return in progress. 5.Br no 94- P1-6N6 piles completed, pcc for pile cap completed. pile cap completed. P2&P3-all piles6x2 are completed. P-2 & P3 Pile cap completed. A2-15N15 piles completed. 6.Br no 106- A1&A2- 18N18 piles completed. pile cap is completed. A2-3rd lift of abutment completed. P2&P2- 6N6 piles completed. P1-Pile Cap Completed. 7.Br no 112- A1-Raft completed. 7th lift of abutment completed. 5th lift of return completed. P2- Raft completed. A2- Raft completed. 8.Br no 115- A1&A2-RCC Raft completed. A1-4th lift completed abutment and return. A2-5th lift of abutment completed along with 4th lift of return wall completed. 9.Br no 116- A2- Concreting of raft Abutment 4th lift completed. Return wall 1st lift completed. A1- Raft foundation completed. 5th lift of Abutment is completed. Return wall 2nd lift completed. BOQ tender for formation, minor bridges & other works are published on 22/03/2025 and 24/03/2025. Opened on 30.04.2025 under evaluation.Detailed Estimate sanctioned by Railway Board vide letter dt. 3.02.2023. SRP notification on 08.02.23 and competent authority notification on 28.03.23. Land Acquisition proposal for issuing 20A notification submitted on 10.04.23. 20A notification issued on 20.11.23. JMS in progress, 4/25 completed. EPC tender to be invited after land acquisition. EPC tender for rest of work is in preparation. Critical Issues: Land acquisition. 93 hectare land required [only 61% of required land available] Wonder Cement Siding,Tulsigram - Timba-Tulsigram section planned only for Goods during the year. Timba to WCL-GCT section GC work inspected by committee on 8.03.2024 and certified fit for goods traffic @ 30 Kmph from Timba to WCL vide letter dt. 12.03.2024. TDC : 4.5 Km: Commissioned for Goods (Timba-WCL) 10.0 Km: Dec.25 (Timba-Desar Road) 39.0 Km: July.26 (Desar Road-Samlaya)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks