Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : SAMNI-JAMBUSAR (24.08 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   61.47

Time Overrun (Months)-    -59

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
216.72349.93349.93

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
021.03021.03

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20300/04/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1250

Ministry Review Date

LatestLastPhysical Progress (%)Status
2Ongoing

Monthly Status

Background Information

Detailed Estimate sanctioned by Railway Board vide letter dt.17.05.2022. Lay foundation stone of project done by Honble PM shri Narendra Modi on 18.06.22. The project declared as Special Railway Project. Special Land Acquisition Officer has been nominated. All Govt 3.5802 Ha land acquired. Land Acquisition of 34.4402 Ha of Pvt. Land, 20 E for 9 villages out of 12 villages of 6.8 Ha of Private land published on 10.01.24. Balance 27.6388 Ha pvt. land, is in linear length of 1.02 km consisting of Jambusar Yard, Samni Yard & at km 56.50 for which 20A received from SDM Jambusar on 06.03.2024 and sent for publication on 15.03.24. Hearing of 20 A is in process by SDM Jambusar. Award for Land from SSNL (0.5583 Ha) is under process by SDM Jambusar. EPC tender awarded on 23.10.2023, Completion period 24 Month. Dismantling of old track completed. Work is in progress. TDC : 13 km - Feb 25 (SAMNI-AMOD) : 11.08 km - April 26 (AMOD-JAMBUSAR)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone