Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 61.47
|
Time Overrun (Months)-
-59
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Detailed Estimate sanctioned by Railway Board vide letter dt.17.05.2022. Lay foundation stone of project done by Honble PM shri Narendra Modi on 18.06.22. The project declared as Special Railway Project. Special Land Acquisition Officer has been nominated. All Govt 3.5802 Ha land acquired. Land Acquisition of 34.4402 Ha of Pvt. Land, 20 E for 9 villages out of 12 villages of 6.8 Ha of Private land published on 10.01.24. Balance 27.6388 Ha pvt. land, is in linear length of 1.02 km consisting of Jambusar Yard, Samni Yard & at km 56.50 for which 20A received from SDM Jambusar on 06.03.2024 and sent for publication on 15.03.24. Hearing of 20 A is in process by SDM Jambusar. Award for Land from SSNL (0.5583 Ha) is under process by SDM Jambusar.
EPC tender awarded on 23.10.2023, Completion period 24 Month. Dismantling of old track completed. Work is in progress.
TDC : 13 km - Feb 25 (SAMNI-AMOD)
: 11.08 km - April 26 (AMOD-JAMBUSAR) | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |