Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH CENTRAL RAILWAY.
Project Name : MUGHALSARAI - ALLAHABAD - 3RD LINE.

Reported Date : 09-JUL-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2649.4402390

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
83.10083.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20260/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3000

Ministry Review Date

LatestLastPhysical Progress (%)Status
55Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks