Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH CENTRAL RAILWAY.
Project Name : ALIGARH-HARDUAGANJ FLYOVER (22 KM).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1456.891244.131456.89

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
10.140010.14

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20260/06/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
150150

Ministry Review Date

LatestLastPhysical Progress (%)Status
04-JUN-258.1Ongoing

Monthly Status

Background Information

Land acquisition is being perused.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks