Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : ADRAJ MOTI-VIAJAPUR (39.75 KM).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
296.540296.54

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
138.12.5225.83164.47

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20307/20255/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
150121

Ministry Review Date

LatestLastPhysical Progress (%)Status
80Ongoing

Monthly Status

Background Information

Adraj Moti-Limodara (17.64 Km) targetted for commissioning in July’25. Engine run completed on 17.64 Km on date 28.03.2025, in Adraj Moti-Limbodara section. Commissioning is planned along with Limbodra-Vijapur in July’25

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Land Acquisition0/00/0PendingImmediateTotal Land required- 15.39 HA (Govt.- 0.67 HA + Pvt- 14.72 HA ) in 13 villages. Total Land Acquired - Govt. Nil Ha, Pvt.- Nil Ha
Utility shiftng0/00/0PendingImmediateTotal Scope: 4 Nos (220 KV) 2 Nos completed and 2 Nos (220 KV) shifting work is progress.TDC-June-25