Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : ADRAJ MOTI-VIAJAPUR (39.75 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
296.540296.54

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0019.5719.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20307/20255/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
150121

Ministry Review Date

LatestLastPhysical Progress (%)Status
55Ongoing

Monthly Status

Background Information

Adraj Moti-Limodara (17.64 Km) target for commissioning in July’25 Engine run done successfully on 17.64 Km on dated 28.03.2025, In Adraj Moti-Limbodara section. Commissioning is planned along with Limbodra-Vijapur in July’25 i.e., Adraj Moti- Limbodara-Vijapur as a whole. Limbodara-Vijapur (22.11 KM) – July’25

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Land Acquisition0/00/0PendingImmediatePara 104 for all 13 villages is in progress. Notification under 20E is to be done by State Govt.
Utility shiftng0/00/0PendingImmediateTotal Scope: 4 Nos (220 KV) , 2 Nos completed and 2 Nos (220 KV) shifting work is progress. TDC-June-25.

Ongoing Milestone

Completed Milestone

   <