Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Adraj Moti-Limodara (17.64 Km) target for commissioning in July’25
Engine run done successfully on 17.64 Km on dated 28.03.2025, In Adraj Moti-Limbodara section. Commissioning is planned along with Limbodra-Vijapur in July’25 i.e., Adraj Moti- Limbodara-Vijapur as a whole.
Limbodara-Vijapur (22.11 KM) – July’25
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
Land Acquisition | 0/0 | 0/0 | Pending | Immediate | Para 104 for all 13 villages is in progress. Notification under 20E is to be done by State Govt. |
Utility shiftng | 0/0 | 0/0 | Pending | Immediate | Total Scope: 4 Nos (220 KV) , 2 Nos completed and 2 Nos (220 KV) shifting work is progress. TDC-June-25. |
| Ongoing Milestone | | Completed Milestone | | |