Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 24.25
|
Time Overrun (Months)-
-27
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
• Dismantling of track completed.
• Civil- The last invited EPC bid was discharged due to an extremely high rate on 19.07.2023. After
discharge of EPC tender, two tenders for civil work containing all activities NIT were re-issued on
31.07.2023, Bid opened on 22.08.2023, contract awarded on 18.10.2023.
• Elect-Contract for modification of 11 KV HT track crossing awarded on 02.02.2023. Tender for
modification of 66 KV- 5 Nos EHT track crossing awarded on 06.11.23. Tender for General Electrical
works awarded on 10.11.23. Tender for OHE Technical Bid opened on 23.11.23 and case with TC.
• S&T-Tender for Kadi station including LCs awarded on 26.08.23, for Block section awarded on
14.09.23 & work is in progress.
• Engine Run was done between Kalol-Kadi-Katosan Road on 26.23 Km (as against the target of 18
Km for the FY 2023-24 | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |