Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
-16
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
NALIYA-JAKHAU PORT (NL) (28.88 Km) TDC – Sept-26 Contract for Major Bridges in Govt. Land has been awarded on 20.08.2024 and tender for other works under process of invitation.
Approximately 86.259 Ha land is to be acquired in 2 villages. Project has been declared as Special Railway Project on 16.02.2023 to expedite the Land Acquisition.
Notification under Section 20E issued.
Land Acquisition is in final stage.
| Detailed project report/Detailed estimate sanctioned on 22.02.2023. Aproximately 120.33 hect. land required. Project has been declared as Special Railway Project to expedite the Land Acquisition on 16.02.2023. SRP notification has been issued. Nomination of Land Acquisition Officer is done by the state Government on 23.11.2023.
Land acquisition proposals (Total 86.31 Ha in 2 villages) for issuing 20A notification already submitted to Land Acquisition Officer.
Notification under section 20A has been issued on 15.01.24.
Land acquisition is in process.
Tender for construction of Major Bridges invited on 17.02.24 and to be opened on 11.03.2024 For balance portion tender will be invited after land acquisition process is completed. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
Land Acquisition | 0/0 | 0/0 | Pending | Immediate | |
| Ongoing Milestone | | Completed Milestone | | |