Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
-22
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Detailed project report/Detailed estimate sanctioned on 22.02.2023. Aproximately 120.33 hect. land required. Project has been declared as Special Railway Project to expedite the Land Acquisition on 16.02.2023. SRP notification has been issued. Nomination of Land Acquisition Officer is done by the state Government on 23.11.2023.
Land acquisition proposals (Total 86.31 Ha in 2 villages) for issuing 20A notification already submitted to Land Acquisition Officer.
Notification under section 20A has been issued on 15.01.24.
Land acquisition is in process.
Tender for construction of Major Bridges invited on 17.02.24 and to be opened on 11.03.2024 For balance portion tender will be invited after land acquisition process is completed. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |