Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : NEW BG LINE BETWEEN NALIYA-JAKHAU PORT.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    -22

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
410.46410.46410.46

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0000

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20280/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
50

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

Detailed project report/Detailed estimate sanctioned on 22.02.2023. Aproximately 120.33 hect. land required. Project has been declared as Special Railway Project to expedite the Land Acquisition on 16.02.2023. SRP notification has been issued. Nomination of Land Acquisition Officer is done by the state Government on 23.11.2023. Land acquisition proposals (Total 86.31 Ha in 2 villages) for issuing 20A notification already submitted to Land Acquisition Officer. Notification under section 20A has been issued on 15.01.24. Land acquisition is in process. Tender for construction of Major Bridges invited on 17.02.24 and to be opened on 11.03.2024 For balance portion tender will be invited after land acquisition process is completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone