Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH CENTRAL RAILWAY.
Project Name : AGRA FORT-BANDIKUI.

Reported Date : 09-JUN-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1389.810987.83

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
42.460042.46

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20275/20265/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
150200

Ministry Review Date

LatestLastPhysical Progress (%)Status
12Ongoing

Monthly Status

Background Information

Tree counting is completed for non TTZ area. Work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks