Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 4.41
|
Time Overrun (Months)-
-3
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
i) EPC agency is available for the entire length for Penukonda - Dharmavaram section for an amount of Rs. 263.66 Cr.
ii) Penukonda- Makkajipalli section (12 Km) was commissioned on 28.02.2025.
iii) Works is under progress and Makkajipalli - Nagasamudram (15 Km) & Nagasamudram - Dharmavaram (15 Km) section.
iv) Entire land has been handed over by GoAP. | i) EPC agency is available for the entire length for Penukonda - Dharmavaram section for an amount of Rs. 263.66 Cr.
ii) Works is under progress.
iii) Entire land has been handed over by GoAP. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |