Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : MALUGUR-PALASAMUDRAM (17.98 KM) (PB#29/NR/2022-23).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    3

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
323.140323.14

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
039.41.0539.46

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20250/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2041.5

Ministry Review Date

LatestLastPhysical Progress (%)Status
12Ongoing

Monthly Status

Background Information

i) Land sub-estimate for Malugur - Palasamudram has been vetted by Accounts for an amount of Rs. 47.05 Cr on 17.08.23 and the same was sanctioned by GM on 30.09.2023. ii) EPC tender for the section is under preparation. iii) Entire land has been handed by GoAP.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone