Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
24
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
i) Tender for placing of boundary posts along the alignment is finalized.
ii) EPC tender from Kyarakoppa - Mammigatti (11.7 km) was called on 06.02.2023 for Rs.244 Cr. and Initial tender opening date was 06.06.2023 and further extended upto 20.12.2023, subjected to handing over to land by GoK. However, due to non availability of land, the tender was canceled on 27.11.2023.
iii) JMC for land acquisition between Kyarakoppa - Tegur has been completed for 25.3 Km out of 26.7 Km. Balance JMC of 1.4Km has been held up due to objections of local farmers. A meeting was conducted with the District in charge Minister of Dharwad and DC Dharwad on 18.11.2023 and 23.12.2023 to resolve the issue. However, farmers did not agree for the same. Further, Hon’ble District Incharge Minister of Dharwad informed that he would inspect the site to resolve the issue in the first week of Jan 2024.
iv) JMC for land acquisition between 26.7 km to 60.0 km Tegur- Bagewadi is yet to start. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |