"i) Land acquisition is in progress.
ii) Meeting was conducted on 16.04.2025 by Sec/IDD along with Hon’ble Infrastructure Minister to review the progress of work and all land issues was highlighted & requested to resolve early.
iii) CE/CN/II/UBL vide letter dt 22.04.2025 has requested IDD/GoK has informed the decision of Railways that no further change in alignment will not be feasible.
iv) IDD Gok vide letter Dtd 16.05.2025 has informed, As per opinion of DC Dharwad new alignment as worked out for Mummigatti village SWR may submit the LA proposal to KIADB - Dharwad.
v) CAO/C vide letter dated 27.05.2025 has requested IDD/GoK to confirm the cost sharing principles of the project cost and to advice DC/Dharwad to undertake land acquisition as per the alignment approved by IDD/GoK vide letter dated 16.05.2025." | i) Tender for placing of boundary posts along the alignment is finalized.
ii) EPC tender from Kyarakoppa - Mammigatti (11.7 km) was called on 06.02.2023 for Rs.244 Cr. and Initial tender opening date was 06.06.2023 and further extended upto 20.12.2023, subjected to handing over to land by GoK. However, due to non availability of land, the tender was canceled on 27.11.2023.
iii) JMC for land acquisition between Kyarakoppa - Tegur has been completed for 25.3 Km out of 26.7 Km. Balance JMC of 1.4Km has been held up due to objections of local farmers. A meeting was conducted with the District in charge Minister of Dharwad and DC Dharwad on 18.11.2023 and 23.12.2023 to resolve the issue. However, farmers did not agree for the same. Further, Hon’ble District Incharge Minister of Dharwad informed that he would inspect the site to resolve the issue in the first week of Jan 2024.
iv) JMC for land acquisition between 26.7 km to 60.0 km Tegur- Bagewadi is yet to start. |