Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 12.94
|
Time Overrun (Months)-
-1
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
i) Land acquisition is still in the initial stages. Meeting was conducted under the chairmanship of ACS/IDD and CAO/CN to discuss Land Acquisition issues pertaining to New Railway Lines on 16.11.2022 and he has stated that priority will be given only to ongoing New line cost sharing projects.
ii) Requisition has been given to DC/HAS for Belur 92.71 ha and Alur 109.86 ha of land on 28/08/2023 and 28/11/2023 respectively. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |