Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : HASSAN (ALUR) - BELUR (32 KM) (UMBRELLA WORK PB#23/2018-19/NR).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   12.94

Time Overrun (Months)-    -1

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
663.03748.85748.85

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
.34.48.06.88

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20280/03/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
1Ongoing

Monthly Status

Background Information

i) Land acquisition is still in the initial stages. Meeting was conducted under the chairmanship of ACS/IDD and CAO/CN to discuss Land Acquisition issues pertaining to New Railway Lines on 16.11.2022 and he has stated that priority will be given only to ongoing New line cost sharing projects. ii) Revised land requisition has been given to DC/HAS for Belur 92.71 Ha and Alur 109.86 ha of land on 28/08/2023 and 28/11/2023 respectively. An additional land requirement of 4.25 Ha - requisition submitted on 06-04-2024. iii) Land acquisition is in progress. iv) A meeting was conducted by GM/SWR with CS/IDD/GoK on 19.09.2024 to expedite the land acquisition of new line projects and other issues involved in the cost sharing projects. v) Meeting was conducted with Railways under the chairmanship of Secretary IDD/GoK on 30.01.2025 with Sectretary IDD/GoK and all concerned DCs.i) Land acquisition is still in the initial stages. Meeting was conducted under the chairmanship of ACS/IDD and CAO/CN to discuss Land Acquisition issues pertaining to New Railway Lines on 16.11.2022 and he has stated that priority will be given only to ongoing New line cost sharing projects. ii) Requisition has been given to DC/HAS for Belur 92.71 ha and Alur 109.86 ha of land on 28/08/2023 and 28/11/2023 respectively.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone