i) Work is in progress for the new line section between Koteganguru & Shikaripura (39.38 km).
ii) In Phase-II (Shikaripura-Ranebennur), land acquisition proceedings like preliminary survey was initiated by KIADB. Survey for land acquisition is in progress. Tender will be called after 90% land is acquired.
iii) For the financial year 2024-25, an amount of Rs. 150 Cr. is requested from GoK vide letter No.W.63/CN/BNC/Bud/E8193 dated 19.03.2024. However, no amount has been deposited.
iv) A meeting was conducted by GM/SWR with CS/IDD/GoK on 19.09.2024 to expedite the land acquisition of new line projects and other issues involved in the cost sharing projects.
v) Meeting was conducted with Railways under the chairmanship of Secretary IDD/GoK on 30.01.2025 with concerned DCs. | i) In Phase-II (Shikaripura-Ranebennur), land acquisition proceedings like preliminary survey was initiated by KIADB. Survey for land acquisition is in progress.
ii)Work is in progress for the new line section between Koteganguru & Shikaripura (39.38 km). |