Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : SHIMOGA-SHIKARIPURA-RANEBENNUR (UMBRELLA WORK PB#23/2018-19/NR).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1453.73994.47994.47

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
43.3424.073.470.81

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20270/012/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
150150

Ministry Review Date

LatestLastPhysical Progress (%)Status
7Ongoing

Monthly Status

Background Information

i) Work is in progress for the new line section between Koteganguru & Shikaripura (39.38 km). ii) In Phase-II (Shikaripura-Ranebennur), land acquisition proceedings like preliminary survey was initiated by KIADB. Survey for land acquisition is in progress. Tender will be called after 90% land is acquired. iii) For the financial year 2024-25, an amount of Rs. 150 Cr. is requested from GoK vide letter No.W.63/CN/BNC/Bud/E8193 dated 19.03.2024. However, no amount has been deposited. iv) A meeting was conducted by GM/SWR with CS/IDD/GoK on 19.09.2024 to expedite the land acquisition of new line projects and other issues involved in the cost sharing projects. v) Meeting was conducted with Railways under the chairmanship of Secretary IDD/GoK on 30.01.2025 with concerned DCs.i) In Phase-II (Shikaripura-Ranebennur), land acquisition proceedings like preliminary survey was initiated by KIADB. Survey for land acquisition is in progress. ii)Work is in progress for the new line section between Koteganguru & Shikaripura (39.38 km).

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone