Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 115.17
|
Time Overrun (Months)-
32
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
i) Total land required 336.68 Ha, Land required in Bangalore Rural dist : 137.80 Ha, Land required in Kolar dist : 198.88 Ha, Govt. of Karnataka is yet to initiate land acquisition proceedings although requisition to acquire land has been submitted by Railways during the year 2013 itself. Hence work could not be commenced.
ii) CAO/CN/BNC vide letter No. W.193/CN/BNC/WFD-KQZ/NL dt 31.07.2023 has requested IDD/GoK to fix priority for the project and intimate their consent for reviewing the detailed estimate of the project with the latest rates.
iii) Subsequently, IDD/GoK has examined the proposal submitted by SWR and decided not to accord the concurrence for the proposal vide their letter No. IDD 03 NSW 2023 dt 31.10.2023 and the same was communicated to the Railway board vide letter dt 18.12.2023.
iv) Further, CAO/CN/BNC has requested PCOM/UBL vide letter dt 05.01.2024 to review the requirements of this project and accordingly to fix the priority of this project. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |