Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : WHITEFIELD-KOLAR (52.9 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   115.17

Time Overrun (Months)-    32

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
162.13348.85348.85

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
.3600.36

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20280/012/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

i) Total land required 336.68 Ha, Land required in Bangalore Rural dist : 137.80 Ha, Land required in Kolar dist : 198.88 Ha, Govt. of Karnataka is yet to initiate land acquisition proceedings although requisition to acquire land has been submitted by Railways during the year 2013 itself. Hence work could not be commenced. ii) CAO/CN/BNC vide letter No. W.193/CN/BNC/WFD-KQZ/NL dt 31.07.2023 has requested IDD/GoK to fix priority for the project and intimate their consent for reviewing the detailed estimate of the project with the latest rates. iii) Subsequently, IDD/GoK has examined the proposal submitted by SWR and decided not to accord the concurrence for the proposal vide their letter No. IDD 03 NSW 2023 dt 31.10.2023 and the same was communicated to the Railway board vide letter dt 18.12.2023. iv) Further, CAO/CN/BNC has requested PCOM/UBL vide letter dt 05.01.2024 to review the requirements of this project and accordingly to fix the priority of this project.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone