Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH CENTRAL RAILWAY.
Project Name : BHANDAI - FLYOVER FOR ETAWAH BOUND DOWN TRAINS.

Reported Date : 09-JUL-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
187.210250.17

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1.29001.29

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20250/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
8Ongoing

Monthly Status

Background Information

Land acquisition work is under progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks