Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : SAHJANWA - DOHRIGHAT.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
371.7701319.75

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
551.74017.41569.15

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20290/06/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2050

Ministry Review Date

LatestLastPhysical Progress (%)Status
3Ongoing

Monthly Status

Background Information

TDC for commissioning of the project June-27TDC for commissioning of the project Mar-27

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks