Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
6
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Project will complete in following two phases:-
Phase-I Bahraich- Nanpara Gauge Conversion (36.51 Km) Target date of commissioning: June-2025
Phase-II Nanpara- Nepalganj Road Gauge Conversion (20.54 Km)Target date of commissioning:June-2025 | Track 08 minor bridges 02 major bridge have been dismantled in BRK-NNP section. Construction of formation is in progress in BRK-RS section.
TDC-Mar-25 |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |